RECON was awarded this project after presenting and receiving approval from the EPA on our technical approach plan.

trucks on site
  • Imported approximately 1,185,000 cubic yards of onsite borrowed material
  • Installed 27-inch cap over regraded tailings area
  • Constructed 20,000 linear feet of channels and swales
  • Constructed three concrete cutoff walls and interim ponds
  • Constructed crest berm with fill material generated from borrow areas
  • Restored over 275 acres of disturbed area